Navy Updates Bayside Dr. Vacant Building Demolition Schedule

On Monday, September 8, 2014, the Navy’s contractor CB&I will begin abatement of asbestos-containing materials within Buildings 1207, 1209, 1211, and 1213. Following asbestos removal Buildings 1207, 1209, 1211, and 1213 will be demolished.  The demolition of vacant buildings on Northpoint Drive is anticipated to begin in October following the demolition work on Bayside Drive. 

Click here for the full notice, which provides additional information about the planned work and who you can contact for more information.

 What to Expect?

During asbestos removal nearby residents may see plastic sheeting installed on doors and windows, set up of air exchanging machines, workers in Tyvek suits, workers on the roof, and roll-off trash bins. During demolition work nearby residents will see large scale demolition equipment, water trucks, dump trucks, and additional truck traffic entering and exiting the fenced area. These measures are intended to prevent the release of any asbestos containing materials. Air monitoring will be performed continuously throughout the removal activity. No road closures are anticipated. Construction trucks will be marked and covered during transport activities.

Schedule

• Asbestos removal is scheduled to start on September 8.

• Building Demolition is planned for September 17 and continue through September 30 at Bayside Drive.

• Work hours are from 7:30 a.m. to 3:00 p.m., Monday through Friday.