Development Construction Overview

Upcoming TICD Construction Activities

Start Date Location Activity Completion Date (Est.)
2/16/18 Administration Building Marina/Market access pathway and parking lot infill 2/23/18
2/19/18 Building 146 Fencing and demolition 2/28/18
2/20/18 Ave of Palms/California Ave MUNI 25 stop closures/relocation Permanent
2/21/18 Clipper Cove Way/Marina Parking Lot Street and lot closure June 2018

Construction-Related Traffic Circulation, Street Closures and Parking Restrictions

Beginning February 20, 2018 TICD construction activities along Treasure Island Road and around Treasure Island's Front Gate and southern and western waterfronts will close on-Island streets and realign traffic circulation.  Full installation of traffic control and traffic safety measures, construction site fencing, access restrictions and directional signage associated with the closures and realignment is scheduled for completion in mid-March 2018.

Motorists, pedestrians, cyclists and MUNI-25 riders can expect street closures and detours, closure and relocation of MUNI 25 stops, closure of public parking areas and re-alignment of on-Island streets and local traffic circulation, in addition to an increase in construction related vehicles and traffic during regular weekday, daytime work hours.

Click here for full information on Phase 1 impacts including site diagrams and downloadable/printable Construction Advisories

Community Construction Meetings

Treasure Island Community Development (TICD) hosts monthly Community Construction Meetings in order to keep the Island community updated on upcoming construction work and expected on-Island impacts due to the work.  All members of the Island community are invited and welcomed to attend.

  • When: Second Wednesday of each month at 6:00 PM - NOTE: February 2018 meeting rescheduled for Wednesday February 21st
  • Where: ShipShape Community Center, 850 Avenue I, Treasure Island

View and download TICD's recent Community Construction Meeting Presentations:

Current Areas of Activity

Map of YBI Development Sub-Phases

Ti Development Construction Phase 1 Map

Navigation Links:

Other Projects Currently Active On-Island (non-TICD):

Public Oversight of Demolition Activities

All Land Use Development proposals by Developers are first reviewed for environmental impacts under the requirements of the state California Environmental Quality Act (CEQA). The environmental review conducted in accordance with CEQA identifies mitigation measures to reduce significant environmental effects. Prior to approval of a project, TIDA adopted feasible mitigation measures identified in the environmental document.  TICD is required to follow the mitigation measures adopted by TIDA such as requiring the best available technology for heavy vehicle emissions control.

For larger projects and those with sensitive receptors within 1000 feet, TICD must submit a Dust Control Plan for San Francisco Department of Public Health (DPH) approval to comply with Article 22B of the Health Code. This approved Dust Control Plan is required prior to TICD, or their contractors, receiving a permit to demolish or build from the San Francisco Department of Building Inspection (DBI). When asbestos-containing building materials will be disturbed, the Developer also has requirements imposed by the Bay Area Air Quality Management District (BAAQMD), the region’s air quality protection agency.

DBI will be sending a field inspector to the Yerba Buena Island and Treasure Island demolition sites regularly to observe that dust control practices are preventing visible dust. DPH has limited inspection resources, but does send inspectors to the site regularly to also observe that dust control practices are effectively preventing visible dust.